s.63Approval of statement of charges by Office
63
Section 63Part 8Interconnection and Electricity Infrastructure Sharing

Approval of statement of charges by Office

←→ Navigate  ·  Click subsection badges to collapse  ·  Press ? for help

63. (1) A T&D licensee shall send each statement prepared in accordance with section 62 to the Office for approval and the statement, and in particular any charges referred to therein, shall not apply until such time as the statement has been approved by the Office, but once approved shall, as appropriate, have retroactive effect to the date the interconnection was established.
The Office shall consult with, and have regard to any submission made by, the T&D licensee, the applicant under section 60 or 61 or a Generator to the Office prior to making a decision whether or not to approve a statement submitted under subsection (1).